With nearly 200 tradespeople working on our hospital daily, great progress is being made on both the interior and exterior of our new facility.
Most of the brick and stone has been installed on the building’s exterior, and workers have shifted their focus to canopy and entrance columns, as well as stonework around the chapel. Exterior windows and skylights are mostly done as well.
Inside, drywall hanging and finishing are well underway, and our vision is becoming a reality as painting and ceiling installations have begun throughout the building.
With the wet summer we’ve had, another major milestone was recently hit as paving began for roadways and parking lots, with curbs and sidewalks also taking shape.