Margaret Mary Monday: Week 7

Home / News / Margaret Mary Monday: Week 7
Choose your content:

As you drive by our Six Pine Ranch campus, you’ll notice an improved view of our new hospital now that the large industrialized construction center tent has been removed from the front.

The workforce is steadily increasing, with an average of 160 tradespeople working on the project daily throughout June. The exterior is taking shape with ongoing brick and stone masonry, and window installations are progressing. Preparations for curbs and asphalt paving have also started.

Inside the building, progress is being made on mechanical, electrical and plumbing systems. Framing and drywall installation also continue, and painting has begun, adding a fresh touch to the interior.

MMH interior

MMH windows

Additional News

MMH Building Front

Community Open House

A new chapter in healthcare is about to begin, and you’re invited to be part of it! Join us on Sunday, August 2, from 11 a.m. to 3 p.m. for ...

Learn more
Margaret Mary Health

Margaret Mary Monday

With less than six weeks until our grand opening, the final details are coming together at our new hospital. Our chapel is now complete, featuring the beautiful etched glass windows ...

Learn more
MMH Donor Wall

Margaret Mary Monday

This week, we’re excited to share photos of our custom donor recognition wall, located in the main lobby of our new hospital. Our community truly came together to make this ...

Learn more